UPCOMING WORK
It is anticipated that there is approximately five to six more weeks of major construction to take place:
· Two more weeks of utility work (finishing sanitary and watermain services, followed by storm sewer)
· One to two weeks for grading the street base
· Two weeks for installing curb and paving the street